1. New Period
Used to separate a part of the schedule and apply changes to that period. (Within the original dates of the schedule)
- Split for a period of time.
- Split on frequency.
- Split on both period and frequency.
 
2. Delete Period
Used to delete period of the schedule. (Within the original dates of the schedule)
Note: Can not be used to delete on frequency.
 
3. << Move
Used to shift the whole schedule one day backward.
Note: Can be pressed several times.
 
4. Expand Period
Used to make the schedule expand, can also be used to alter the frequency.
- To expand the period of the schedule.
- To add frequency days to the schedule.
- To remove frequency days from the schedule.
Note: If you want to expand to a frequency day not currently in the period, you will have to expand the dates to cover that day as well.
Note: If you want to change the frequency for the whole period, you need to use this button, otherwise it is not going to work properly.
 
5. Reduce Period
Used to reduce the schedule period, can also be used to reduce frequency.
- To reduce the period of the schedule.
- To remove frequency days from the schedule.
Note: If you want to remove some frequencies for the whole period, you need to use this button, otherwise it is not going to work properly.
 
6. Move >>
Used to shift the whole schedule one day forward.
Note: Can be pressed several times.
                

                                                    